High Level Project Phases

Reference below for a rough breakdown of key milestones for the lead up and follow through for the remodel here at The 355.

The basic steps leading up to permits are categorized as follows:

  • Proposal
  • Preliminary
  • Permit Ready

Meaning that when the target scope is revised and clarified the architecture and design phase(s) are realized in Proposal form. Iterations will be expected, but the objective is to clarify and constrain scope

Next, these Preliminary drawings will be reconciled by way of rough ballpark estimates from builders and undergo preliminary review by San Mateo County Planning and Building. It is key to make sure the proposed plan is realistic from construction and budget standpoint. Lessons learned and review steps would refine the plans to Permit Ready state.


Stages and Milestones

The steps are mapped to the higher level stages distilled out from getting a handle about how to work with San Mateo County Planning and Building staff over time. Reference the San Mateo County - Reference Excerpts content for more detail.

I. Architecture and Design —> II. Engineering Due Diligence —> III. San Mateo County - Planning and Review Steps —> IV. San Mateo County - Building Permit Phase —> V. Buid —> VI. Inspection Phase

These differentiated states surfaced from past discussions with builders and have shaped our interest to identify potential builder(s) very early on in the process to provide guidance where needed.

STEPDESCRIPTIONTARGETSTATUS
0Boundary Survey and Topographic MappingSummer 2023Completed
I.ARCHITECTURE AND DESIGN:
1As Built PlansSummer 2023Completed
2aArchitecture and Design Iterations - Master SouthCQ4 2023 - CQ3 2024Stopped
2bArchitecture and Design Iterations - Master NorthCQ4 2024 - CQ1 2025Pending
2cArchitecture and Design - Proposal Draft Plans ReadyCQ4 2024 - CQ1 2025Pending
3Preliminary Drawings - Builder ReviewC4 2024 - CQ2 2025Pending
II.ENGINEERING DUE DILIGENCE:
4Geotechnical, Structural Analysis and Review, Identify and Mitigate Code Compliance or Non-conforming IssuesCQ4 2024, CQ1 2025Pending
III.San Mateo County - PLANNING and REVIEW STEPS:
5County Planning and Review: Coastal Development Permit, COASTSIDE Design Review Committee, COASTSIDE Fire Protection District, San Mateo County - Coastal Zone: Drainage ReviewSpring-Summer 2025
6Permit Ready PlansSummer 2025
IV.San Mateo County - BUILDING PERMIT PHASE:
7Building: Permit Phase: building, mechanical, electrical, fire, geotechnical, plan check, filing, microfilm, health, and planning feesSummer 2025
V.BUILD:
8Building PhaseLate Summer 2025, Early Spring 2026
VI.INSPECTION PHASE:
9Building: Inspections and finaling